Liverpool Wind Energy Storage Project | Watts Wind Energy

The Liverpool Wind Energy Storage Project

Project Update

Located in Liverpool, Nova Scotia, construction of this 2 turbine project began in June 2016. The project entered commercial operations in June 2017.

Site Photos

Timeline

  • Comfit Award Date: May 20, 2014
  • Met Tower Install Date: April 2015
  • Construction Start Date: Spring 2016
  • Wind Turbine In Service Date: Fall 2016

Technical Details

Turbine Specs

  • COMFIT Capacity Awarded: 3.6MW
  • Size: 2 Turbines
  • Make: Enercon
  • Model: E92
  • Hub Height: 95M
  • Rotor Diameter: 92M

Investment Information

This project is part of the Nova Scotia COMFIT program.
Invest now.